Completed Projects - 2009
 
2009 Projects by Township

Updated: March 17, 2010

 

Select a township by clicking on the map below.

ALL TOWNSHIPS
ROAD / LOCATION PROJECT NOTES
Various County and township roads Centerline and edgeline restriping / retracing COMPLETE. Cost: $240,103. Funding: BCEO & twps
Various County-maintained intersections Installation of UPS battery backup for traffic signals COMPLETE. Cost: $95,995. Funding: BCEO
Various County roads Ditching / mowing / weed spraying Seasonal, ongoing maintenance. Funding: BCEO FA
 
FAIRFIELD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
LIBERTY FAIRFIELD RD Bridge #03.803 (over Great Miami River) Replacement and roadway realignment COMPLETE. Cost: $10,312,716. Funding: Federal, State, BCEO
News release - ground breaking.

News release - ribbon cutting.
Image: View project plan overlay on aerial photo
Photos: Click for Lib Ffd Rd Bridge photos page
MORRIS RD culvert near Alexis Dr Removal COMPLETE. Cost: $6,805. Funding: BCEO FA (labor)
MORRIS RD - Ham Mason Rd to Ffd North Elem Resurfacing COMPLETE. 0.7 mile. Cost: $59,534. Funding: Ffd Twp
RENTSCHLER FOREST PRESERVE & MIAMI-ERIE CANAL METROPARK Storm erosion damage repairs COMPLETE. Cost: $18,830. Funding: BCEO FA (labor), BC MetroParks (materials)
RIVER RD Bridge #00.722 Replacement COMPLETE. Cost: $534,612. Funding: State OPWC, BCEO, City of Ffd
News release.

Photo: Old bridge - top view
Photo: Old bridge - side view
Photo: Construction - top view
Photo: Construction - top view
RIVER RD - Ham Co line to Ffd corp & Ffd corp to Lake Circle Dr Resurfacing, install raised pavement markers COMPLETE. 1.1 miles. Cost: $270,541. Funding: Fed - American Recovery & Reinvestment Act (stimulus)
TULEY RD - Alston Av to Tylersville Rd Resurfacing COMPLETE. 0.7 mile. Cost: $76,870. Funding: Ffd Twp
 
HANOVER TOWNSHIP
ROAD / LOCATION PROJECT NOTES
DARRTOWN RD - Nichols Rd to Milford Twp line Resurfacing COMPLETE. 0.5 mile. Cost: $56,298. Funding: Han Twp
DARRTOWN RD - Ohio 130 to dead end Resurfacing COMPLETE. 1.0 mile. Cost: $79,334. Funding: Han Twp
DECAMP RD - Stillwell Beckett Rd to south 1,820 ft Resurfacing (SAMI seal) COMPLETE. 0.7 mile. Cost: $23,248. Funding: Han Twp
GARDNER RD - Hamilton corp to Beissinger Rd Resurfacing COMPLETE. 0.5 mile. Cost: $65,549. Funding: Han Twp
HOGUE RD - Ohio 177 to St. Clair Twp line Resurfacing (SAMI seal) COMPLETE. 1.9 miles. Cost: $52,336. Funding: Han Twp
LANES MILL RD Culvert #02.089 Replacement COMPLETE. Cost: $40,193. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - top view
Photo: New culvert - outlet side
RAHFUSE AV - Pearle Ln to chip seal section Resurfacing (SAMI seal) COMPLETE. 0.1 mile. Cost: $1,790. Funding: Han Twp
ROSS HANOVER RD - U.S. 27 to Millville village line Resurfacing COMPLETE. 0.5 mile. Cost: $78,878. Funding: State CDBG
VIZEDOM RD - Ohio 177 to south 173 ft Resurfacing COMPLETE. 0.1 mile. Cost: $6,191. Funding: Han Twp
WASHBURN RD - Ohio 177 to pvt bridge Resurfacing (SAMI seal) COMPLETE. 0.2 mile. Cost: $5,842. Funding: Han Twp
 
LEMON TOWNSHIP
ROAD / LOCATION PROJECT NOTES
None
 
LIBERTY TOWNSHIP
ROAD / LOCATION PROJECT NOTES
CHABLIS DR - Moselle Dr to Mogul Ln Resurfacing COMPLETE. 0.3 mile. Cost: $37,413. Funding: Lib Twp
DUTCHLAND PKWY near Liberty School Sidewalk installation COMPLETE. Cost: $27,440. Funding: Fed LPA
FORT LIBERTY PARK - parking lot Resurfacing COMPLETE. Cost: $76,093. Funding: Lib Twp
HAMILTON MASON RD - Mauds Hughes Rd to 1,230 ft east Resurfacing COMPLETE. 0.2 mile. Cost: $29,380. Funding: Lib Twp
I-75 - Cincinnati Dayton Rd to Middletown corp Widen to 4 lanes in each direction, upgrade interchanges at Ohio 63 and Ohio 122 Under construction. Completion: 2010. ODOT project. Cost: $98,824,590.
Complete project details.
I-75 at OHIO 129 (Liberty Way Interchange) Expanded interchange - distributor/collector road for new hwy access to Ham Mason Rd and Cox Rd COMPLETE. TID project. Phase 3 of Ohio 129 / I-75 interchange expansion (Liberty Interchange). TID project in conjunction with ODOT, OKI, Lib Twp, WC Twp, BCEO. New ramps to Ham Mason Rd (Lib Way) constructed in conjunction w/ ODOT I-75 widening project. Cost: $14,742,859. Funding: But Co, Lib Twp, WC Twp. Under construction eff mid-08. Completed: Oct 09.
Schematic: New ramps and roadway configurations.
Artist sketch: Aerial sketch of new interchange
IMPERIAL DR - Willow Brooke Dr to 1,500 ft east Resurfacing COMPLETE. 0.3 mile. Cost: $27,281. Funding: Lib Twp
LIBERTY WAY at TYLERS PLACE BLVD New signals COMPLETE. Full operation Oct 15.
LIBERTY WAY (formerly HAM MASON RD) - Cincinnati Dayton Rd to I-75 Roadway improvement - widen to 5 lanes COMPLETE. TID project. Phase 4 of Ohio 129 / I-75 interchange expansion (Liberty Interchange). Cost: $3,901,099. Funding: BC TIF, Lib & WC Twp. Under construction. Completed: Oct 09.
LIBERTY FAIRFIELD RD Bridge #03.803 (over Great Miami River) Replacement and roadway realignment COMPLETE. Cost: $10,312,716. Funding: Federal, State, BCEO
News release - ground breaking.

News release - ribbon cutting.
Image: View project plan overlay on aerial photo
Photos: Click for Lib Ffd Rd Bridge photos page
LOGSDON'S WOODS DR - at subdivision entrance Resurfacing COMPLETE. Cost: $3,337. Funding: Lib Twp
MAUDS HUGHES RD - at Ham Mason Rd Guardrail repairs COMPLETE. Funding: BCEO FA
MILLIKIN RD between Snow Hill and 747 Ditching, berm repairs COMPLETE. Funding: BCEO FA
PROVIDENCE RIDGE DR - Walnut Creek Dr to 600 ft east Resurfacing COMPLETE. 0.1 mile. Cost: $15,092. Funding: Lib Twp
WALNUT CREEK DR - Ham Mason Rd to 920 ft north Resurfacing COMPLETE. 0.2 mile. Cost: $29,181. Funding: Lib Twp
WHIPOORWILL WAY - Beech Knoll Ln to Moselle Dr Resurfacing COMPLETE. 0.1 mile. Cost: $11,729. Funding: Lib Twp
WILLOW BROOKE DR - Princeton Rd to 1,350 ft north Resurfacing COMPLETE. 0.3 mile. Cost: $33,581. Funding: Lib Twp
 
MADISON TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BERTHA AV - Keister Rd to dead end Resurfacing COMPLETE. 0.1 mile. Cost: $11,893. Funding: Mad Twp
BEVERLY LN - Ohio 122 to cul-de-sac Resurfacing COMPLETE. 0.3 mile. Cost: $31,629. Funding: Mad Twp
DAIRY LN - Trenton Franklin Rd to dead end Resurfacing COMPLETE. 0.1 mile. Cost: $11,115. Funding: Mad Twp
ELK CREEK RD - Ohio 122 to West Alexandria Rd Resurfacing (SAMI seal) COMPLETE. 1.5 miles. Cost: $57,766. Funding: BCEO
LIBERTY FAIRFIELD RD Bridge #03.803 (over Great Miami River) Replacement and roadway realignment COMPLETE. Cost: $10,312,716. Funding: Federal, State, BCEO
News release - ground breaking.

News release - ribbon cutting.
Image: View project plan overlay on aerial photo
Photos: Click for Lib Ffd Rd Bridge photos page
MAY AV - Ohio 122 to cul-de-sac Resurfacing COMPLETE. 0.2 mile. Cost: $17,787. Funding: Mad Twp
WAYNE MADISON RD at AUGSPURGER RD Install signals Start: Oct. Completion: Jan 2010. Est cost: $100,000. Funding: BCEO
 
MILFORD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BAUER RD Bridge #02.048 Replace w/ box culvert COMPLETE. Cost: $260,019. Funding: State OPWC, BCEO
Photo: Old bridge - top view
Photo: Old bridge - side view
Photo: Construction - top view west
Photo: Construction - top view west
Photo: Construction - top view east
Photo: Construction - inlet side
Photo: Construction - outlet side
Photo: New bridge - top view east
Photo: New bridge - top view west
Photo: New bridge - side view
HAMILTON EATON RD north of State Rd Roadside slip repairs (erosion from Seven Mile Creek) COMPLETE. Cost: $157,187. Funding: BCEO (State OPWC 0-percent loan)
Photo: Original stream bank erosion near road - view downstream
Photo: Original stream bank erosion near road - view downstream
Photo: Complete - view downstream
Photo: Complete - view downstream
Photo: Complete - view upstream
Photo: Complete - view upstream
HUSTON RD - Taylor School Rd to Scott Rd Resurfacing (SAMI seal) COMPLETE. 1.0 mile. Cost: $29,879. Funding: BCEO
LANES MILL RD Culvert #02.476 Replacement, roadside erosion repairs COMPLETE. Cost: $30,047. Funding: BCEO FA
Photo: New culvert - inlet side
Photo: New culvert - outlet side
Photo: Ditching, flow and erosion repairs
LANES MILL RD Culvert #03.047 Replacement COMPLETE. Cost: $19,334. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
Photo: New guardrail at culvert site
OXFORD MIDDLETOWN RD - Oxford Milford Rd to 0.9 mile east Resurfacing COMPLETE. 0.9 mile. Cost: $58,100. Funding: Mil Twp
SCOTT RD - Ohio 177 to Huston Rd Resurfacing (SAMI seal) COMPLETE. 2.8 miles. Cost: $96,666. Funding: BCEO
SOMERVILLE RD Bridge #05.345 (over Williams Run) Replacement COMPLETE. Cost: $453,329. Funding: State OPWC, BCEO
Photo: Old bridge - top view
Photo: Old bridge - side view
Photo: New bridge - top/side view west
Photo: New bridge - top view east
Photo: New bridge - underside view
STATE RD - Ham Eaton Rd to Ohio 744 Resurfacing (SAMI seal) COMPLETE. 2.7 miles. Cost: $95,665. Funding: BCEO
Township parking lot Resurfacing COMPLETE. Cost: $37,091. Funding: Mil Twp
US 127 - Way Twp line to Preble Co line Resurfacing, install raised pavement markers COMPLETE. Funding: Fed - American Recovery & Reinvestment Act (stimulus)
 
MORGAN TOWNSHIP
ROAD / LOCATION PROJECT NOTES
ALERT NEW LONDON RD - California Rd to Schradin Rd Resurfacing COMPLETE. 1.3 miles. Cost: $89,137. Funding: Mor Twp
BUELL RD - Ohio 126 to dead end Resurfacing (SAMI seal) COMPLETE. 0.6 mile. Cost: $19,706. Funding: Mor Twp
CANN RD - Alert New London Rd to dead end Resurfacing (SAMI seal) COMPLETE. 0.1 mile. Cost: $2,875. Funding: Mor Twp
HOWARD RD Bridge #01.640 (over Howard's Creek) Replacement COMPLETE. Cost: $217,493. Funding: State OPWC, BCEO
Photo: Old bridge - top view
Photo: Old bridge - side view
Photo: Construction
Photo: Construction
Photo: Complete - top view west
Photo: Complete - side view north
Photo: Complete - side view south
RACE LANE RD - short section near new culverts Resurfacing COMPLETE. 0.1 mile. Cost: $3,800. Funding: Mor Twp
 
OXFORD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BOOTH RD at CSX RR Crossing repair COMPLETE. Funding: CSX
COLLEGE CORNER Village Ditching/drainage improvements COMPLETE. Cost: $48,932. Funding: State CDBG
TODD RD Culvert #00.241 Replacement COMPLETE. Cost: $18,037. Funding: BCEO FA (labor), Oxf Twp (materials)
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
TODD RD Culvert #01.139 Replacement COMPLETE. Cost: $13,334. Funding: BCEO FA (labor), Oxf Twp (materials)
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
TODD RD Culvert #01.257 & #01.261 Replacement (combine into one culvert) COMPLETE. Cost: $18,826. Funding: BCEO FA (labor), Oxf Twp (materials)
TODD RD Culvert #01.473 Replacement COMPLETE. Cost: $4,886. Funding: BCEO FA (labor), Oxf Twp (materials)
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
TODD RD Culvert #01.766 Replacement COMPLETE. Cost: $11,802. Funding: BCEO FA (labor), Oxf Twp (materials)
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
TODD RD Culvert #02.689 Replacement COMPLETE. Cost: $8,953. Funding: BCEO FA (labor), Oxf Twp (materials)
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
TODD RD - Oxford city corp to Jones Rd Resurfacing COMPLETE. 2.6 miles. Cost: $190,821. Funding: Oxf Twp
 
REILY TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BOOTH RD at CSX RR Crossing repair COMPLETE. Funding: CSX
DECAMP RD - Stillwell Beckett Rd to south 1,820 ft Resurfacing (SAMI seal) COMPLETE. 0.7 mile. Cost: $23,248. Funding: Han Twp
DUNWOODY RD Culvert #01.890 Replacement COMPLETE. Cost: $9,289. Funding: BCEO FA (labor), Rly Twp (materials)
GARNER RD Culvert #00.379 Replacement COMPLETE. Cost: $4,386. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
GARNER RD Culvert #00.850 Replacement COMPLETE. Cost: $11,325. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
GARNER RD Culvert #01.840 Replacement COMPLETE. Cost: $19,826. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
GARNER RD Culvert #01.885 Replacement COMPLETE. Cost: $26,860. Funding: BCEO FA
Photo: Old culvert - outlet side
GARNER RD - Ohio 129 to Reily Millville Rd Resurfacing (SAMI seal) COMPLETE. 2.4 miles. Cost: $106,979. Funding: BCEO
HART RD - Dunwoody Rd to Peoria Reily Rd Resurfacing (strip patch berms) COMPLETE. 1.7 miles. Cost: $15,920. Funding: Rly Twp
NORTH WEAVER RD - Dunwoody Rd to Peoria Reily Rd Resurfacing (strip patch berms) COMPLETE. 2.0 miles. Cost: $18,213. Funding: Rly Twp
NORTH WEAVER RD - Peoria Reily Rd to Springfield Rd Resurfacing (SAMI seal) COMPLETE. 0.8 mile. Cost: $15,878. Funding: Rly Twp
REILY MILLVILLE RD - Ohio 732 to Bunker Hill Woods Rd Resurfacing & installation of raised pavement markers COMPLETE. 2.2 miles. Cost: $266,849. Funding: BCEO
STAHLHEBER RD - South Pierson Rd to Han Twp line Resurfacing COMPLETE. 0.5 mile. Cost: $42,563. Funding: Rly Twp
STEPHENSON RD at CSX RR Crossing repair COMPLETE. Funding: CSX
STILLWELL BECKETT RD Culvert #04.083 Replacement COMPLETE. Cost: $8,819. Funding: BCEO FA
Photo: Old culvert - top view, outlet side
Photo: Old culvert - inlet side
Photo: New culvert - top view, outlet side
STILLWELL BECKETT RD Culvert #04.141 Replacement COMPLETE. Cost: $9,073. Funding: BCEO FA
Photo: Old culvert - top view, outlet side
STILLWELL BECKETT RD Culvert #04.183 Replacement COMPLETE. Cost: $32,538. Funding: BCEO FA
Photo: Old culvert - top view, inlet side
Photo: Old culvert - top view, outlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
STILLWELL BECKETT RD at CSX RR Crossing repair COMPLETE. Funding: CSX
STILLWELL BECKETT RD - Ohio 732 to Woods Stn Rd Resurfacing & installation of raised pavement markers COMPLETE. 2.9 miles. Cost: $329,612. Funding: BCEO
 
ROSS TOWNSHIP
ROAD / LOCATION PROJECT NOTES
CINCINNATI BROOKVILLE RD - Ham Co line to Ohio 128 Resurfacing COMPLETE. 0.6 mile. Cost: $76,514. Funding: BCEO
JAY PHILLIP CT - Timberman Rd to dead end Resurfacing COMPLETE. 0.1 mile. Cost: $6,845. Funding: Ros Twp
ROBINA LN - Brown Farm Dr to dead end Resurfacing (SAMI seal) COMPLETE. Cost: $4,823. Funding: Ros Twp
ROSS HANOVER RD - U.S. 27 to Millville village line Resurfacing COMPLETE. 0.5 mile. Cost: $78,878. Funding: State CDBG
SORBUS DR - at Platanus Dr Resurfacing COMPLETE. 0.1 mile. Cost: $14,272. Funding: Ros Twp
TIMBERMAN RD - Smith Rd to Ham New London Rd Resurfacing COMPLETE. 1.7 miles. Cost: $93,340. Funding: Ros Twp
 
ST. CLAIR TOWNSHIP
ROAD / LOCATION PROJECT NOTES
AUGSPURGER RD Culvert #02.161 Replacement COMPLETE. Cost: $6,616. Funding: BCEO FA
BEISSINGER RD - Eaton Rd to curves west Roadway improvements - ease curves, replace culverts, improve drainage, improvements to Eaton/Beissinger intersection COMPLETE. Cost: $602,644. Funding: State OPWC, BCEO
Photo: Previous curve
Photo: Construction
Photo: Complete - view west
Photo: Complete - view west
EATON RD Culvert #04.874 Replacement COMPLETE. Cost: $8,069. Funding: BCEO FA
EATON RD at BEISSINGER RD See Beissinger Rd above COMPLETE (intersection portion only). See Beissinger Rd above
LIBERTY FAIRFIELD RD Bridge #03.803 (over Great Miami River) Replacement and roadway realignment COMPLETE. Cost: $10,312,716. Funding: Federal, State, BCEO
News release - ground breaking.

News release - ribbon cutting.
Image: View project plan overlay on aerial photo
Photos: Click for Lib Ffd Rd Bridge photos page
SHARON PARK Catch basin replacements COMPLETE. Cost: $24,531. Funding: State CDBG
TRENTON RD at CSX RR Crossing repairs COMPLETE. Funding: CSX
US 127 - Trenton Rd to Village of Seven Mile Resurfacing, install raised pavement markers COMPLETE. Funding: Fed - American Recovery & Reinvestment Act (stimulus)
WAYNE MADISON RD at AUGSPURGER RD Install signals Start: Oct. Completion: Jan 2010. Est cost: $100,000. Funding: BCEO
 
WAYNE TOWNSHIP
ROAD / LOCATION PROJECT NOTES
JACKSONBURG RD Culvert #03.307 Replacement COMPLETE. Cost: $17,349. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - outlet side
JACKSONBURG RD Culvert #08.136 Replacement COMPLETE. Cost: $12,870. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side (left pipe)
JACKSONBURG RD Culvert #08.148 Replacement COMPLETE. Cost: $12,870. Funding: BCEO FA
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side (right pipe)
Photo: New culvert - outlet side
SHURZ RD - Ohio 744 to Stubbs Rd Resurfacing COMPLETE. 1.1 miles. Cost: $77,429. Funding: Way Twp
Photo: Complete near Stubbs
US 127 - Village of Seven Mile to Way Twp line Resurfacing, install raised pavement markers COMPLETE. Funding: Fed - American Recovery & Reinvestment Act (stimulus)
US 127 at N&S RR Crossing repairs COMPLETE. Funding: N&S
WAYNES TRACE RD Culvert #02.007 Replacement COMPLETE. Cost: $10,081. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - outlet side
WAYNES TRACE RD Culvert #03.676 Replacement COMPLETE. Cost: $8,462. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - outlet side
Photo: New culvert - outlet side
WAYNES TRACE RD Culvert #03.788 Replacement COMPLETE. Cost: $7,241. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
WAYNES TRACE RD Culvert #05.597 Replacement COMPLETE. Cost: $9,958. Funding: BCEO FA
Photo: Old culvert - top view
Photo: Old culvert - inlet side
Photo: Old culvert - outlet side
Photo: New culvert - inlet side
Photo: New culvert - outlet side
 
WEST CHESTER TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BECKETT RD - Smith Rd to UCB Roadway improvements - ease curve, add turn lanes at park, replace culvert, add bike path COMPLETE. Cost: $1,463,590. Funding: WC Twp TIF
News release.

Video
Photo: Original road - view SE at curve
Photo: Original road - view SE
Photo: Original road - view north
Photo: Old culvert
Photo: Construction - easing curve
Photo: Construction - clearing for bike path along road
Photo: Construction - new pavement laid at north curve
Photo: Construction - new pavement at north curve
Photo: Construction - new pavement, grading slope
Photo: Construction - retaining wall
Photo: Construction - top view of retaining wall
Photo: Construction - top view of retaining wall
Photo: Construction - view north toward south curve
Photo: Construction - new pavement
Photo: Construction - retaining wall nears completion
Photo: Construction - completion at north curve
Photo: Construction - widening, view south toward UCB
CINCINNATI DAYTON RD at DIMMICK RD and UCB Roadway improvements - turn lane additions, signals, new streets for GE development COMPLETE. Est cost: $1,000,000. Funding: private
CRESCENTVILLE RD at OHIO 747 Intersection improvement - additional turn lane COMPLETE. ODOT project. Est cost: $3,120,000. Funding: Fed, BCEO, City of Springdale
HAMILTON MASON RD - Mauds Hughes Rd to 1,230 ft east Resurfacing COMPLETE. 0.2 mile. Cost: $29,380. Funding: Lib Twp
I-75 - Cincinnati Dayton Rd to Middletown corp Widen to 4 lanes in each direction, upgrade interchanges at Ohio 63 and Ohio 122 Under construction. Completion: 2010. ODOT project. Cost: $98,824,590.
Complete project details.
LIBERTY WAY (formerly HAM MASON RD) - Cincinnati Dayton Rd to I-75 Roadway improvement - widen to 5 lanes COMPLETE. TID project. Phase 4 of Ohio 129 / I-75 interchange expansion (Liberty Interchange). Cost: $3,901,099. Funding: BC TIF, Lib & WC Twp. Under construction. Completion: late 09. Some closures necessary.
MAUDS HUGHES RD - at Ham Mason Rd Guardrail repairs COMPLETE. Funding: BCEO FA
OHIO 747 at N&S RR Crossing repairs COMPLETE. Funding: N&S
OHIO 747 at DEVITT DR and INTERSTATE DR Install signals at Devitt & 747. Construct connector road between dead-ends of Devitt and Interstate Dr COMPLETE. ODOT project. Est cost: $535,233. Funding: Federal
PORT UNION RD near LeSaint Dr Westbound lane addition COMPLETE. Cost: $159,449. Funding: State DOD, BCEO
TYLERSVILLE RD Culvert #04.599 Replacement COMPLETE. Cost: $18,238. Funding: BCEO FA
TYLERSVILLE RD Culvert #04.628 Replacement COMPLETE. Cost: $4,606. Funding: BCEO FA
TYLERSVILLE RD Culvert #06.412 Replacement COMPLETE. Cost: $28,326. Funding: BCEO FA
TYLERSVILLE RD - Bypass 4 to Cox Rd Resurfacing, install raised pavement markers COMPLETE. 6.0 miles. Cost: $1,810,541. Funding: Fed - American Recovery & Reinvestment Act (stimulus)
UNION CENTRE BLVD - West Chester Rd to Muhlhauser Rd Roadway improvement - add lane in each direction COMPLETE. Cost: $1,648,257. Funding: WC Twp TIF
Photo: Roadway before construction - view west
UNION CENTRE BLVD at FLOER DR Install new signals COMPLETE. Funding: WC Twp TIF
UNION CENTRE BLVD at IMAGINATION BLVD Install new signals at new intersection Under construction. Completion: Jan 2010. Cost: $271,583. Funding: WC Twp TIF
Various township/subdivision streets Resurfacing, slurry seal, black matt COMPLETE. Est cost: $1,615,977. Funding: WC Twp
 
 