Current Projects - 2020
 
2020 Projects by Township

Updated: April 2, 2020

COVID19 STAY AT HOME ORDER HAS PROMPTED US TO PUT OUR CULVERT MAINTENANCE PROJECTS ON HOLD. OUR OPERATIONS DEPT. IS STILL RESPONDING TO URGENT ISSUES DURING THIS TIME.

IMPROVEMENT PROJECTS INCLUDING PAVING ARE PROCEEDING, SOME WITH MINOR DELAYS.

• For specific road closing and opening information, click here.
• This list is ongoing and dynamic. Notes/status will be updated. New projects may be added or current projects may be moved to Future status.
• Project questions? Email us.

2020 Capital Improvements Report

Select a township by clicking on the map below.

ALL TOWNSHIPS
ROAD / LOCATION PROJECT NOTES
Various County and township roads Centerline and edgeline restriping / retracing - paint Est cost: tbd. Funding: BCEO, townships
Various County roads Ditching / mowing / weed spraying Seasonal, ongoing maintenance. Funding: BCEO FA
 
FAIRFIELD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BROFIELD DR at MILLIKIN RD
Culvert
Replacement Road closure necessary. Start: early May. Completion: 3 days. Est. cost: $13,412. Funding: BCEO FA
CANAL RD
Culvert #1.612
Replacement Road closure necessary. Start: early May. Completion: 3 days. Est. cost: $6,992. Funding: BCEO FA
CANAL RD
Culvert #1.657
Replacement Road closure necessary. Start: early May. Completion: 3 days. Est. cost: $14,217. Funding: BCEO FA
GILMORE RD
S.R. 129 overpass to new Gilmore Road/roundabout
Roadway improvement - widen, add2-way left-turn lane, storm sewer, sidewalk, access road Est. cost: $1,235,000. Funding: Fairfield Twp TIF
LIBERTY FAIRFIELD RD - Princeton Rd to Millikin Rd Roadway improvement - widen to 3 lanes (addition of center turn lane), widen shoulders , install lighting at intersections, adjust vertical profile IN PROGRESS - to be completed in 2020 construction season -Contract cost: $5,554,340. Funding: Fed, BCEO
Photo: Existing condition
Photo: Construction
Photo: Construction
Photo: Construction
Various township / subdivision streets Resurfacing (asphalt) Est cost: $462,843. Funding: FF Twp
Various township / subdivision streets Resurfacing (black mat) Est cost: $135,905. Funding: FF Twp
 
HANOVER TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BOYLE RD
Culvert #0.172
Replacement Road closure necessary. Start: August. Completion: 10 days. Est. cost: $30,100. Funding: BCEO FA
BOYLE RD
Culvert #1.256
Replacement Road closure necessary. Start: mid-August. Completion: 10 days. Est. cost: $25,500. Funding: BCEO FA
LANES MILL RD
Culvert #0.512
Replacement Road closure necessary. Start: May. Completion: 5 days. Est. cost: $21,455. Funding: BCEO FA
LANES MILL RD
Culvert #0.595
Replacement Road closure necessary. Start: mid-May. Completion: 5 days. Est. cost: $19,908. Funding: BCEO FA
LANES MILL RD
Culvert #2.007
Replacement Road closure necessary. Start: late May. Completion: 10 days. Est. cost: $29,841. Funding: BCEO FA
LANES MILL RD
Culvert #2.256
Replacement Road closure necessary. Start: June. Completion: 3 days. Est. cost: $13,520. Funding: BCEO FA
LANES MILL RD Slope repair Road closure necessary. Start: late June. Completion: 2 wks. Est. cost: $25,350. Funding: BCEO FA
Various township / subdivision streets Resurfacing (asphalt repair) Est cost: $33,726. Funding: Hanover Twp
Various township / subdivision streets Resurfacing (chip seal) Est cost: $162,546. Funding: Hanover Twp
 
LEMON TOWNSHIP
ROAD / LOCATION PROJECT NOTES
HOWE RD
Culvert #3.492
Replacement Road closure necessary. Start: late April. Completion: 5 days. Est. cost: $24,951. Funding: BCEO FA
 
LIBERTY TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BETHANY RD
Culvert
Replacement (for Liberty Twp) Construction starts: late March. Completion:10 days. Road closure necessary. Est cost: $30,0001. Funding: Liberty Twp
CINCINNATI DAYTON RD
Culvert #08.216
Replacement Construction starts: June/July. Completion: 4 days. Road closure necessary. Est cost: $20,049. Funding: BCEO
CINCINNATI DAYTON RD
Culvert #09.561
Replacement IN PROGRESS. Requires a 30-day road closure. Est cost: $198,428. Funding: BCEO

HAMILTON MASON RD

Hamilton Mason Corridor Improvement - Phase 1

Bridge #07.491 (over Gregory Creek)

Bridge Replacement.

Phase 2 will be the Hamilton Mason Rd. @ Mauds Hughes Intersection Improvement in 2022.

Est. cost: $1,800,000. Funding: State OPWC, local
Photo: Existing bridge - top view
Photo: Existing bridge - side view
KYLES STATION RD
Mauds Hughes Rd to Yankee Rd
Resurfacing (asphalt) Est cost: $307,463. Funding: BCEO
KYLES STATION RD
Yankee Rd to Cincinnati Dayton Rd
Resurfacing (asphalt) Est cost: $132,007. Funding: BCEO
KYLES STATION RD
Culvert #05.139
Replacement Road closure necessary. Start: late March. Completion 10 days. Est cost: $36,104. Funding: BCEO FA
KYLES STATION RD
Culvert #04.032
Replacement Road closure necessary. Start: late April. Completion 10 days. Est cost: $35,703. Funding: BCEO FA
KYLES STATION RD
Culvert #03.532
Replacement Road closure necessary. Start: late April. Completion 15 days. Est cost: $41,200. Funding: BCEO FA
LIBERTY FAIRFIELD RD Princeton Rd to Millikin Rd Roadway improvement - widen to 3 lanes (addition of center turn lane), widen shoulders , install lighting at intersections, adjust vertical profile IN PROGRESS - will be completed in 2020 construction season -Contract cost: $5,554,340. Funding: Fed, BCEO
Photo: Existing condition
Photo: Construction
Photo: Construction
Photo: Construction
LINN RD
Culvert #0.509
Replacement Road closure necessary. Start: late April. Completion: 3 days. Est cost: $12,673. Funding: BCEO FA
MILLIKIN RD
Intersection at Lib. FF Rd
Resurfacing (asphalt) Est. cost: $28,952. Funding: BCEO
MILLIKIN RD
East of S.R. 747
Surface repair Est. cost: $2,809. Funding: BCEO
PRINCETON RD
S.R. 747 to Mauds Hughes Rd (west)
Resurfacing (asphalt) Est cost: $536,505. Funding: BCEO
PRINCETON RD
Mauds Hughes (east) to Cincinnati Dayton Rd
Resurfacing (asphalt) Est cost: $357,320. Funding: BCEO
PRINCETON RD
Culvert #7.120
Replacement Road closure necessary: late March. 4 days. Est cost: $25,350. Funding: BCEO FA
PRINCETON RD
Culvert #7.870
Replacement Road closure necessary: late March. 5 days. Est cost: $8,075. Funding: BCEO FA
PRINCETON RD
Culvert #8.77
Replacement Road closure necessary: late March. 2 days. Est cost: $5,025. Funding: BCEO FA
Various township / subdivision streets Resurfacing (asphalt) Est cost: $693,153. Funding: Lib Twp
Various township / subdivision streets Resurfacing (black mat seal) Est cost: $235,425. Funding: Lib Twp
 
MADISON TOWNSHIP
ROAD / LOCATION PROJECT NOTES
ELK CREEK RD
Culvert #02.353
Replacement Est cost: $178,050. Funding: BCEO
ELK CREEK RD Surface repair Est cost: 20,901. Funding: BCEO
MIDDLETOWN GERMANTOWN RD
Corlee Ln to Preble County line
Resurfacing (asphalt) Est cost: $363,528. Funding: BCEO
MIDDLETOWN GERMANTOWN RD
Bridge #00.393
Replacement Est cost: $200,000. Funding: BCEO
Photo: Esisting bridge -top view
Photo: Existing bridge - side view
MIDDLETOWN GERMANTOWN RD
Culvert #0.556
Replacement Est cost: $30,350. Funding: BCEO
TRENTON FRANKLIN RD
Bridge #5.758
Pour concrete bottom Start: October Est cost: $35,235. Funding: BCEO FA
TRENTON FRANKLIN RD at MICHAEL RD Drainage improvements, ditching, guardrail replacement Road closure necessary. Completion: 2 weeks. Est cost: $73,675. Funding: BCEO FA
WEST ALEXANDRIA RD Culvert #0.049 Replacement Start: mid-May, 3 days Est. cost: $7,785. Funding: BCEO FA
WEST ALEXANDRIA RD Culvert #1.875 Replacement Start: mid-May, 6 days Est. cost: $12,150. Funding: BCEO FA
WEST ALEXANDRIA RD Bridge #1.420 Pour concrete bottom Start: October Est. cost: $7,760. Funding: BCEO FA
WEST ALEXANDRIA RD Bridge #0.661 Pour concrete bottom Start: October Est. cost: $8,025. Funding: BCEO FA
WEST ALEXANDRIA RD S.R. 122 to Elk Creek Rd Resurfacing Est. cost: $465,204. Funding: BCEO
Various township / subdivision streets Resurfacing (asphalt) Est cost: $257,274. Funding: Madison Twp
 
MILFORD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
HAMILTON EATON RD
Old Somerville Corp line to S.R. 744
Resurfacing Est. cost: $25,907. Funding: BCEO
TAYLOR SCHOOL RD
Culvert #1.218
Replacement Road closure necessary. Start: October. Est. cost: TBD. Est. Cost: $5,225. Funding: BCEO FA
Various township / subdivision streets Resurfacing (asphalt) Est cost: $501,450. Funding: Milford Twp
 
MORGAN TOWNSHIP
ROAD / LOCATION PROJECT NOTES
ALERT NEW LONDON RD
at S.R. 126
striping only Est cost: $119.00. Funding: BCEO FA
CALIFORNIA RD
Culvert #0.897
Replacement Road closure necessary. Start: July. Completion: 3 days. Est cost: $12,370. Funding: BCEO FA
CALIFORNIA RD
Culvert #1.171
Replacement Road closure necessary. Start: July. Completion: 3 days. Est cost: $18,201. Funding: BCEO FA
CALIFORNIA RD
Culvert #1.474
Replacement Road closure necessary. Start: July. Completion: 5 days. Est cost: $32,500. Funding: BCEO FA
CALIFORNIA RD
Culvert #1.516
Replacement Road closure necessary. Start: mid-July. Completion: 5 days. Est cost: $35,014. Funding: BCEO FA
CALIFORNIA RD
Culvert #2.987
Replacement Road closure necessary. Start: late July. Completion: 5 days. Est cost: $26,700. Funding: BCEO FA
CALIFORNIA RD
Culvert #2.994
Replacement Road closure necessary. Start: July. Completion: 3 days. Est cost: $12,505. Funding: BCEO FA
CALIFORNIA RD
Culvert #3.051
Replacement Road closure necessary. Start: August. Completion: 3 days. Est cost: $18,050. Funding: BCEO FA
CALIFORNIA RD
Culvert #3.311
Replacement Road closure necessary. Start: August. Completion: 3 days. Est cost: $13,750. Funding: BCEO FA
CALIFORNIA RD
Culvert #3.505
Replacement Road closure necessary. Start: August. Completion: 10 days. Est cost: $35,250. Funding: BCEO FA
CALIFORNIA RD
Culvert #5.199
Replacement Road closure necessary. Start: August. Completion: 3 days. Est cost: $26,040. Funding: BCEO FA
CALIFORNIA RD
Culvert #5.252
Replacement Road closure necessary. Start: September. Completion: 3 days. Est cost: $11,950. Funding: BCEO FA
CALIFORNIA RD
Culvert #5.348
Replacement Road closure necessary. Start: September. Completion: 10 days. Est cost: $26,050. Funding: BCEO FA
CALIFORNIA RD
Culvert #5.532
Replacement Road closure necessary. Start: September. Completion: 3 days. Est cost: $18,425. Funding: BCEO FA
CHAPEL RD
Culvert #2.396
Replacement Road closure necessary. Start: late September. Completion: 3 days. Est cost: $13,225. Funding: BCEO FA
CHAPEL RD
Culvert #3.174
Replacement Road closure necessary. Start: October. Completion: 10 days. Est cost: $30,775. Funding: BCEO FA
LAYHIGH RD
Culvert #2.189
Replacement (for Morgan Twp) Road closure necessary. Start: mid-May. Completion: 20 days. Est cost: $12,150. Funding: Morgan Twp
 
OXFORD TOWNSHIP
ROAD / LOCATION PROJECT NOTES
RIGGS RD
Culvert #1.851
Replacement Road closure necessary. Start: early April. Completion 3 days. Est. cost: $12,653. Funding: BCEO FA
RIGGS RD
Culvert #2.029
Replacement Road closure necessary. Start: early April. Completion 3 days. Est. cost: $15,101. Funding: BCEO FA
RIGGS RD
Culvert #2.517
Replacement Road closure necessary. Start: mid- April. Completion 3 days. Est. cost: $13,025. Funding: BCEO FA
RIGGS RD
Culvert #3.244
Replacement Road closure necessary. Start: mid- April. Completion 6 days. Est. cost: $19,899. Funding: BCEO FA
TALAWANDA DR
Culvert #3.244
Replacement
(for Oxford Twp)
Road closure necessary. Start: late March Completion 3days. Est. cost: $12,331. Funding: Oxford Twp
Various township / subdivision streets Resurfacing (asphalt) Est cost: $122,529. Funding: Oxford Twp
 
REILY TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BUNKER HILL WOODS RD
Culvert #0.088
Replacement Road closure necessary. May, 5 days. Est cost: $10,250. Funding: BCEO FA
BUNKER HILL WOODS RD
Reily Millvile Rd to Stillwell Rd
Resurfacing Est cost: $159,429. Funding: BCEO
BUNKER HILL WOODS RD Stillwell Rd to Garver Elliot Rd Resurfacing Est cost: $209,952. Funding: BCEO
GARVER ELLIOT RD
Bunker Hill Woods Rd to Woods Station Rd
Resurfacing (chip seal) Est cost: $69,460. Funding: BCEO
WOODS STATION RD
Garver Elliot Rd to North Pierson Rd
Resurfacing (chip seal) Est cost: $35,336. Funding: BCEO
 
ROSS TOWNSHIP
ROAD / LOCATION PROJECT NOTES
WARVEL RD
All
Resurfacing (asphalt) Est cost: $197,622. Funding: BCEO
 
ST. CLAIR TOWNSHIP
ROAD / LOCATION PROJECT NOTES
RIVERSIDE DR
Trenton Rd to Trenton Rd
Resurfacing (Asphalt) Est. cost: $287,940. Funding: BCEO
 
WAYNE TOWNSHIP
ROAD / LOCATION PROJECT NOTES
S.R. 73 at JACKSONBURG RD (ODOT PROJECT) Intersection Improvement - install roundabout

Partial intersection closure necessary. ODOT PROJECT

Notice of July 20, 2016 public mtg

TAYLOR SCHOOL RD
Culvert #2.324
Replacement Road closure necessary. Start: October. Completion: 10 days. Est. cost: $5,225. Funding: BCEO FA
TOLBERT RD
Bridge #00.914
Superstructure Replacement Contract cost: $445,000. Funding: BCEO
 
WEST CHESTER TOWNSHIP
ROAD / LOCATION PROJECT NOTES
BECKETT RD
Fire station and Beckett Ridge Blvd
Drainage improvements, resurfacing Est cost: $1,786,606 Funding: BCEO, West Chester Twp TIF
BUTLER WARREN RD at LIBERTY WAY Intersection improvement - add EB left turn lanes and NB left turn lanes Est. cost: $1,077,061. Funding: BCEO.

CINCINNATI DAYTON RD

Culvert #05.357

Replacement Construction start: July. Completion: 10 days. Road closure necessary. Est cost: $35,625. Funding: BCEO FA
LESOURDSVILLE WEST CHESTER RD at BECKETT RIDGE BLVD Intersection Improvement - install roundabout Road closure necessary. Est cost: $1,628,646. Funding: Fed, BCEO
MUHLHAUSER RD
Bridge #00.430
Repair - pour concrete bottom Road closure possible. Completion: 1 week. Est. cost: $22,150. Funding: BCEO FA
TYLERSVILLE RD, PHASE 2
I-75 to Cox Rd
Roadway Improvement - widenting, Additional WB lanes, extend Doc Dr, add access drive, signal modifications at NB I-75 ramp/Dudley Dr/Kingsgate Way, and Cox Rd IN PROGRESS. Contract cost:$3,065,493, Funding: Butler County
TYLERSVILLE RD at CHANTILLY DR Intersection Improvement - add turn lane IN PROGRESS. Contract cost: $377,414. Funding: Fed, BCEO
UNION CENTRE BLVD / I-75 INTERCHANGE Interchange modification - convert to DDI, add lanes to ramps, install ramp metering and signals at ends of entrance ramps, install sidewalks and new mast arm signals

IN PROGRESS - will be completed in 2020 construction season- Start: mid-May 2019. Lane closures with one 4 to 5 day road closure. Completion: mid-late 2020. Contract cost: $19,998,662. Funding: WC Twp TIF
UCB Diverging Diamond PPT presentation (Sep 2018)

Construction 3/11/20 -NB I-75
Construction 3/11/20 -SB I-75

Various township / subdivision streets Resurfacing (asphalt) Est. cost: TBD. Funding: WC Twp
Various township / subdivision streets Resurfacing (black mat seal) Est cost: TBD. Funding: WC Twp
 
 
• Project questions? Email us.